 Talbot/Avoca Road Stage two upgrade

Works to carry out Stage Two of the Talbot/Avoca Road are now underway.

The upgrade includes a full road reconstruction and culvert renewal works.

The one kilometre stretch of road is located either side of the Amherst Cemetery.  

Works are being delivered by Council’s Works team and are expected to take 8 to 10 weeks to complete.

Temporary lane closures may be required during the project. Motorists should obey changed traffic conditions.

The $693,000 project is jointly funded by the State Government Fixing Country Roads Program ($462,000) and Council ($231,000).